To get up to speed we will mention what was completed last week {9*20-9*24}
-The kitchen counter tops and sink went in on Monday.
-Plumbers were there most of the week. We have toilets, sinks and running water.
-electrician came in and finished all the hook-ups. It's neat to even see light bulbs installed!
-The lot was cleaned, leveled, yellow sand was laid (for nutrients),
irrigation was installed and landscaping started (sod and 2nd tree to follow)
-Propane tank and tank-less water heater went in and the propane take was filled.
-End of this week the flooring had begun to be installed.
The coming week will include:
-wood floors to be completed on Monday {takes 3 days to install}
-Sod and tree to also be placed on Monday
-Sod and tree to also be placed on Monday
-hanging of doors and door knobs
-construction clean up
-Dry wall punch. This means the painters come back in and go over all the walls with a fine-toothed comb to ensure touch-ups are complete and there are no blemishes.
By weeks end we are to have our insurance carrier picked because carpet should be installed the following week!!!! Once Howard {builder} has a walk-thru with his boss it will then be our turn to walk-thru with him.